Indian Oil Tenders for 2.75 MW Solar Plant in Trichy
- Indian Oil has provided a tender for establishing of 2.75 MW ground-mounted solar energy project at the firms' LPG bottling plant in Trichy, Tamil Nadu.
The Indian Oil Corporation (IOCL) has issued a tender, inviting bids from eligible prospective buyers for setting up of 2.75 MW ground-mounted solar energy project at the companies' LPG bottling plant in Trichy, Tamil Nadu.
IOCL suggests to set up the 2.75 MWp solar project for restricted intake at several IOCL areas across Tamil Nadu with the Open Access Agreement as well as Energy Wheeling Agreement. The project will certainly be done with an EPC Contractor on LSTK basis.
The scope of work for the chosen prospective buyers will certainly consist of the engineering, purchase and building and construction (EPC) deal with the grid-connected solar project. Which will certainly be followed by 5 years of extensive operation and also upkeep services for the plant, from the day of successful commissioning.
The commissioning of the complete capability of the project need to be completed within 9 months from the day of the website handing over.
The last date for proposal entry is September 22, 2020, and also the techno-commercial buds will be opened on September 23, 2020. A pre-bid meeting has actually been scheduled for September 15, 2020, to attend to the problems elevated by the prospective bidders. All prospective buyers will be needed to submit an Earnest Money Deposit of Rs 9.6 lakh together with their bids, and there is no MSME choice under this tender.
Further, the supplier's service warranty for all gotten products will be offered to the Owner and shall be valid for the entire problem obligation period. As well as, the Manufacturer's/ Contractor's warranty, for any replaced product shall also be offered to the Owner and shall be kept legitimate for the original service warranty duration.
The Photovoltaic modules shall have a product warranty of a minimum of 10 years and also a performance service warranty of 25 years from the day of appointing and also the inverters/ PCUs shall be required for 5 years from the date of appointing and the Supervisory Control and also Data Acquisition (SCADA) System shall be warranted for minimum 5 years.