Trungnam Group launches the largest solar farm in Vietnam in the middle of renewables drive
- Trungnam Group officially ushered in the 500KV transformer station as well as 220/500KV Grid line, as well as the 450 MW Trung Nam Thuan Nam solar power plant on October 12th, 2020 in Phuoc Minh commune, Thuan Nam area of the south-central Ninh Thuan Province. It's a spectacular occasion as well as vital project in celebration of the 14th Ninh Thuan provincial Party's Congress, 2021-2025 terms.
Ninh Thuan province has been a preferred location for numerous renewable energy projects with total capacity approximately 2,000 MW since 2018. The rise investment in the brand-new energy projects in the province succeeded established due to the State's policy and also device in addition to local authorities in supporting renewable energy projects.
According to the National Load Dispatch Centre, 80 solar energy plants with complete capacity of 4,464 MW had been built in the nation up to June 30, 2019. These projects, primarily in Ninh Thuan province, were currently authorized by for providing power to the nationwide grid. Nonetheless, the national power grid was seriously overloaded with mass operation of series solar energy plants in other words term in Ninh Thuan as well as Binh Thuan provinces. Many currently constructed solar power plants might not provide power to the nationwide grid due to overloaded power transmission. Some plants were forced to lower their functioning capacity with an average decrease from 30 per cent to 35 percent, even 60 percent in keeping the national grid functioning security.
The decrease of procedure ability at some plants developed numerous troubles for capitalists in repayment and also operation price in addition to financing for expansion of investment.
The overloaded power transmission system in Ninh Thuan plainly introduced the lack of simultaneous investment in the national grid framework as well as at locals, hence resulting in deficiency of simultaneous investment at local and limit the development of renewable resource projects.
Despite of initiatives from EVN in boosting the nationwide grid as well as power transmission system over previous years, sluggish administrative treatment as well as land clearance at locals had actually postponed the beginning building of grid projects. While renewable energy projects consisting of solar energy plants need only six months to end up, a 220KV or 500KW power transmission project would extract from 3 to 5 years to finish.
Recognizing the problems in growth of power transmission projects, Trungnam Group made a decision to purchase improving the nationwide facilities of power transmission systems, conserving the expense for other renewable energy investors from minimizing operation capacity. The Group approximated that the decrease of renewable energy plants in the province will certainly not be dealt with at 60 per cent due to poor power transmission, however the number would certainly enhance.
As the top leading capitalist in renewable resource in Ninh Thuan province, Trung Nam significantly suggested a financial investment of the 500KV transformer terminal and also 220/500KV Grid line and the 450 MW Trung Nam Thuan Nam solar energy plant with technical assistances and also inspiration from the provincial people's committee as well as EVN.
Following the proposition, Trungnam Group was accepted as a financier of the 500KV transformer station and also 220KV/500KV power transmission system, in integrated of a 450 MW solar power plant under the document No 831/UBND-KTTH sealed on March 18th, 2020, and the choice for investment proposition No 79/Q Đ-UBND on April 3rd, 2020.
Trungnam Group then acceleratory finished legal treatment and also fund as well as manpower for swiftly commencing the project through days and night working shifts in turning over the project in time.
Treatment a location on 557.09 ha including 17km power transmission line from Phuoc Minh neighborhood in Thuan Nam district to Vinh Tan commune of Tuy Phong district of Ninh Thuan Province, Trungnam Group had dealt with the building and construction timetable from May of 2020 to the 4th quarter of 2020.
With a target of finishing the project in 102 days, Trungnam Group had actually finished land clearance procedure in 45 days with the tough working days from 8,000 labourers and also engineers in turning over the project as proposed time of conclusion.
On the celebration of launch of the project, Chairman of Trungnam Group, Mr. Nguyen Tam Thanh was honourly awarded the Labour Order, Second Class from the State for finishing the solar energy plant and also power transmission project, contributing to the development of renewable resource project in Ninh Thuan Province specifically, as well as to the training course of the country's social republic as well as support.
Trungnam Group additionally significantly added to aid regional community as a function and also obligation of a potential financier in Ninh Thuan Province. The Group, in co-operation with the provincial Fatherland Front, Thuan Nam common people's committee and also rural association of poor patients, had actually given away 102 residences worth 5.1 billion Vietnamese dong to poor homes in the district throughout construction of projects here.
1. General information of project
|
Trung Nam Thuan Nam Solar Power plant |
Power Grid and transmission system |
Overall Capacity |
450MW |
Power Transmission Station: Capacity 2 x 900MVA, Dz 500kV, 15.5km long; Dz 220kV, 2km |
Proposal operation time |
September 30, 2020 |
September 30, 2020 |
Proposal output capacity |
1 billion kWh -- an equivalent 1 GWh |
|
Commencing of construction day |
May 15, 2020 |
May 15, 2020 |
Inauguration |
Oct 10th, 2020 |
|
Total investment capital |
12 trillion of Vietnamese dong |
Two trillion Vietnamese dong |
Manpower |
7,000 people |
|
Project Zone (project study area) |
900 hectares |
2. Information of Solar Power Plant, Power Grid and Power transmission systems
|
Items |
Figure |
Specifications |
A |
Solar Power Plant |
||
|
Solar Panel |
1.400.000 |
455 & 460Wp -- Mono 156 Cell |
|
Inverter |
102 sets |
SIEMENS (Germany) 3 phase- 4,560kW |
|
Combiner box |
2.770 boxes |
20 input/box |
|
Power transformer |
4,560kVA |
3 phase, oil immersed transformer |
|
Bracket |
23.900 rows |
10 per cent automatic revolve and 90 per cent fixed system |
|
Wire |
6.000.000m |
Panel connection to overall box |
|
33kV Internal power line and operation systems, SCADA |
||
B |
Power line and power transmission system |
||
|
Transformer station 33/220/500kV |
Two transformers |
SIEMENS – Germany Overall capacity 1,800MVA |
|
500kV Grid -- Double-circuit line |
2km |
500 kV transformer, Thuan Nam Solar power at Van Phong -- Vinh Tan switched point |
|
13.5km |
Van Phong - Vinh Tan switched point in connection with Vinh Tan thermal power plant |
|
|
220kV Line -- 4 circuits |
2km |
500kV Thuan Nam Transformer Station connection with 220kV Vinh Tan -- Thap Cham circuit |
The 500kV and also 220/500kV power line project in integrated with the 450 MW Trung Nam Thuan Nam solar energy plant produces more than 1 billion kWh-- an equal of 1GWh power from renewable enegy (the first year will certainly be 1.2 billion kWh), as well as add to ease overloaded power network in Ninh Thuan province va South-central seaside area. Two transformer terminals of the project, with complete developed capability of 1,800 MVA, in incorporated with power line network will aid improve the procedure of the nationwide grid system in the South main region.
The procedure of the 500kV transformer station as well as 220/500kV high-voltage line network in mix of the 450 MW Trung Nam Thuan Nam solar energy plant will certainly play crucial roles as listed below:
- Contributing to the implementation of Resolution choice of No 115 of the Government on structure Ninh Thuận province a nationwide centre for renewable resource.
- Contributing to making use of total capacity of renewable resource plants in Ninh Thuan and also Binh Thuan provinces, avoiding forced reduction of power generation from solar energy plants that would certainly trigger to the loss of trillions Vietnamese dong of investors every year, as well as improving business atmosphere at the district as commitments between neighborhood authorities as well as capitalists along with handling power scarcity in across the country in context forced reduction of renewable resource projects.
- Supplying an included power ability of greater than 1 billon KWh to the national Grid system every year, improving the development of renewable energy projects in replacing nonrenewable fuel source produced nuclear power plant as well as promoting setting defense.
- In understanding of Resolution Decision No 55 of the Political Bureau in advertising the involvement from economic sector in renewable resource advancement and also power transmission framework system.
The operation of the 500kV transformer terminal as well as 220/500kV power line network in mix of the 450 MW Trung Nam Thuan Nam solar energy plant is an important strategical project in serving the development of power transmission of Ninh Thuan province particularly, and also the central seaside region as a whole, as well as national power transmission framework system. Trungnam Group's project was developed with an investment of 12 trillion Vietnamese dong with a 450MW solar energy plant, 500kV power transformer station and more than 17km of 500kV, 220kV power transmission system from Phuoc Minh neighborhood, Thuan Nam district, to Vinh Tan neighborhood, Tuy Phong district, Binh Thuan province.
The completion and also procedure of 500kV transformer and 220/500kV power transmission system in combination with 450 MW Trung Nam Thuan Nam solar energy plant was seen as a historical landmark of Vietnam power industry in the context of economic sector investing in power transmission system that made renovation from local to central governments.
In addition to successes in financial investment of renewable resource projects including solar power, wind power, Trungnam Group has actually been creating gas discharged power projects adhering to the proposal of Resolution No 55-NQ/TW of the central government in strategy plans in power growth of Vietnam to 2030, vision 2045 that provided by Political Bureau, offering priorities in diversifying versions of renewable resource financial investment as well as preferential plan in operation of renewable resource projects as well as reliable utilities of renewable resource brand-new power, clean energy as well as gas driven power plants.
On the other hands, Trungnam Group is likewise a capitalist in the Ca Na incorporated port in Ninh Thuan province with a proposition conclusion time for full operation of pier No 1 for hosting freight ships from 70.000 to 100.000 DWT in December of 2022.
The port project would certainly assist add in transport equipment, particularly huge devices for renewable energy projects and gas burned power plants in Ninh Thuan district as well as south central seaside area as well as Central Highlands area.
Trungnam Group, that had experience in operation and also building renewable resource projects and readily available workforce, highly verified that it will certainly be a possible capitalist in building huge gas power projects in the future.