Pilecom Begins Construction on 106-MW Lancaster Solar Farm

Jul 18, 2025 11:13 AM ET
  • Pilecom powers up Victoria: 106-MW Lancaster Solar Farm to energize 216 GWh annually, marking European Energy's bold Australian expansion.

Pilecom Pty Ltd has commenced construction on the 106-MW Lancaster Solar Farm in Victoria for European Energy A/S. The project involves installing 23,274 piles, 1,683 single-axis Horizon trackers, and approximately 170,000 solar panels over a 172-hectare site near Kyabram. The solar farm is expected to produce 216 GWh of clean electricity annually, with grid connection planned for 2026.

European Energy acquired the Lancaster project from Sweden's OX2 AB in September 2024, alongside the 31-MWp/25-MW AC Mulwala solar farm in New South Wales. The Danish company entered the Australian market in March 2025 with the 56-MW Mokoan Solar Park and views Lancaster as a key step in its expansion strategy.

What are the key components and timeline of the Lancaster Solar Farm project?

Project Components:

  • Installation of 23,274 piles.
  • Deployment of 1,683 single-axis Horizon trackers.
  • Installation of approximately 170,000 solar panels.
  • Coverage of a 172-hectare site near Kyabram, Victoria.
  • Expected annual electricity production of 216 GWh.

Timeline:

  • September 2024: European Energy acquired the Lancaster project from OX2 AB.
  • March 2025: European Energy entered the Australian market with the Mokoan Solar Park.
  • Construction commencement by Pilecom Pty Ltd.
  • Grid connection planned for 2026.