Israel prepares 800 MW of pumped hydro storage space

Jun 24, 2020 04:46 PM ET
  • Renewables firm Ellomay Capital has actually been forced to reduce the range of its prepared 340 MW Manara Cliff project, in the north of the nation, because 2 competing schemes have actually currently demolished a huge percentage of the capability allocation presently used by the federal government.
Israel prepares 800 MW of pumped hydro storage space
Image: Jotpe/Wikimedia Commons

The Israeli federal government has actually allocated 800 MW of pumped hydro storage, according to the full-year numbers for 2019 published by NYSE-listed Israeli renewables company Ellomay Capital.

The Tel Aviv-based designer is targeting a 156 MW slice of that quota with its Manara Cliff project, although the range of the prepared dual-reservoir facility has actually been decreased from 340 MW, under its most recent conditional permit terms, since competing projects have eaten into the capacity available.

Ellomay, which said its 300 MW Talasol solar area in Extremadura, Spain is 60% built and anticipated to be operational this year, confessed plans are already much more born down a 300 MW pumped hydro facility in the Gilboa region, which is entering its final building stage; and also at the 344 MW Kochav Hayarden system, which is currently incomplete. The latter project is a sore point for Ellomay, which filed two not successful lawful situations objecting to expansions to economic closure and building deadlines afforded the rival facility by the Israeli Electric Authority (IEA) and also the proper priest.

Bet sale

The regards to the brand-new conditional licence given Ellomay for the smaller project give the company up until completion of the year to get to financial closure, at which point Ellomay has specified it would sell 35% of the 75% holding it has in project firm Ellomay Pumped Storage-- by means of subsidiary Ellomay Water Plants Holdings Ltd-- to an unrevealed capitalist. The Manara project would supply energy to the IEA under a power supply offer.

The renewables company confessed can shed additional possible capacity at Manara if any rival project gotten to financial close before it does but specified, in a filing to the U.S. Securities as well as Exchange Commission, it understands a scheduled 156 MW pumped hydro center at Nesher no longer holds a conditional permit.

The Manara project likewise hinges on Ellomay bargaining a reasonable charge to sub-let the project site from national entity the Israel Land Authority (ILA). The renewables business has actually stopped at the NIS160 million ($46.7 million) required by the ILA and also said it was excessive, consisting of the determined worth of NIS1 million for each and every megawatt of set up capacity.

Ellomay's annual report additionally mentioned information of plans to mount a 28 MW solar project near the Talasol site and details of two structure arrangements-- for 250 MW and 365 MW-- it has actually authorized to create new-build solar generation ability in Italy.