Hive Energy Expands Serbian Solar Portfolio with 216 MW

Jun 4, 2024 04:56 PM ET
  • Hive Energy's Serbian solar parks with battery storage are set to power up, adding 216.5 MW to their renewable energy portfolio. More projects in the pipeline!

British renewables developer Hive Energy has secured grid-connection for four solar parks in Serbia, adding a total power generation capacity of 216.5 MW. The projects come with integrated battery energy storage systems, representing 10% of the overall PV capacity. The company expects to continue with urbanism planning procedures in the coming months.

The 50-MW Pirot and 40-MW Prokuplje schemes are set to become shovel-ready between the last quarter of 2024 and the first quarter of 2025, while Veliko Gradiste I and II, with capacities of 71.5 MW and 55 MW, are expected to receive the ready-to-build status shortly after. Hive Energy has a 490-MW Serbian portfolio and plans to sign more grid-connection contracts this month, with additional applications prepared for seven schemes totaling 500 MW. The company opened an office in Belgrade in May 2022 and has 2.2 GW of Serbian solar projects under development.

What is the total power generation capacity of Hive Energy's solar parks in Serbia?

  • The total power generation capacity of Hive Energy's solar parks in Serbia is 216.5 MW
  • The projects include integrated battery energy storage systems representing 10% of the overall PV capacity
  • The Pirot scheme is 50 MW
  • The Prokuplje scheme is 40 MW
  • Veliko Gradiste I has a capacity of 71.5 MW
  • Veliko Gradiste II has a capacity of 55 MW
  • Hive Energy has a 490 MW Serbian portfolio
  • The company plans to sign more grid-connection contracts this month
  • Additional applications are prepared for seven schemes totaling 500 MW
  • Hive Energy has 2.2 GW of Serbian solar projects under development.