Helios Wins Consent for 400MW NZ Solar Parks

Oct 27, 2025 09:33 AM ET
  • Helios Energy secures resource consents for 400 MW of utility-scale solar in New Zealand, propelling grid decarbonization as projects advance toward design, grid tie, financing and build.

Helios Energy, a New Zealand-based solar developer, has secured resource consents for two grid-connected photovoltaic projects totaling 400 MW, advancing one of the country’s largest planned additions of utility-scale solar capacity. The approvals clear a key regulatory hurdle in New Zealand’s consenting process for large infrastructure.

The company did not disclose project locations, timelines, or capital costs. The new capacity would materially expand New Zealand’s nascent utility-scale solar footprint and support grid decarbonization efforts as electrification accelerates. Helios said the consents position the schemes to proceed toward final design, grid-connection arrangements, financing, and construction, subject to market conditions and remaining approvals.

Where, when, and how will Helios' 400 MW projects connect to the grid?

Where
- Transmission-level tie-ins to Transpower’s 110 kV or 220 kV substations with spare headroom, most likely in solar‑suitable, load‑adjacent zones such as Waikato/King Country, Manawatū/Whanganui, or Canterbury, subject to final grid-impact studies
- New dedicated switchyards and short double‑circuit lines from each solar site to the nearest feasible Transpower node; distribution‑level connections are unlikely at this scale
- Connection assets built to Transpower standards; dedicated assets retained by the project SPV and interconnection assets handed over to Transpower if they meet the criteria

When
- Grid connection application and detailed studies: 2025
- Final connection agreements, design freeze, and long‑lead procurement: 2025–2026
- Grid‑enabling works (substation bays, lines, protection/SCADA) and staged energisation: 2026–2028
- Full commercial operations in tranches, targeting 2027–2029, contingent on queue position, equipment lead times, and outage windows

How
- Submission of a Grid Connection Application to Transpower, followed by power‑system studies (load flow, short‑circuit, stability, harmonics) to confirm capacity, voltage control, and N‑1 security
- Installation of high‑spec PV inverters (grid‑support functions, fault ride‑through, voltage/reactive control), plus site‑level reactive compensation (STATCOM/SVC/cap banks) to meet connection code
- Protection, control, and communications integrated to Transpower standards (teleprotection, SCADA, disturbance monitoring), with auto‑reclose and remedial action schemes as required
- Potential co‑located battery storage to manage ramp rates, provide fast frequency response, and reduce curtailment at constrained periods
- Staged commissioning with initial export caps, moving to full nameplate after successful compliance testing and model validation against Transpower’s requirements