Two significant solar-plus-storage projects green-lit in Australia's New South Wales

Mar 11, 2020 11:38 AM ET
  • Programmers of 2 considerable solar-plus-storage projects in the Australian state of New South Wales have actually been given the go-ahead, with only small problems contributed to their propositions.
Two significant solar-plus-storage projects green-lit in Australia's New South Wales
Image: TransGrid

The NSW federal government's Independent Planning Commission accepted the other day (9 March) an AU$ 768 million (US$ 503 million) solar-plus-storage project on the Northern Tablelands, regardless of the suggested growth originally getting 67 public arguments.

Developer UPC Renewables Australia will certainly currently have the ability to start the 720MW New England Solar Farm, which will certainly be incorporated with 200MW/400MWh of lithium-ion battery storage space and also set on 3,362 hectares of farming land, 6 kilometres eastern of Uralla.

Public issues focused on the compatibility of the suggested land usage, the project's aesthetic effects, web traffic monitoring, results on animals, and also the decommissioning as well as rehab of the project as well as land.

The NSW Department of Planning, Industry as well as Environment sent out the application to the Commission for testimonial on 20 December. The Commission after that authorized the project application today, considering it to be in the general public rate of interest, however included a variety of problems.

Deactivating strategy

As presently made, the New England Solar project would certainly consist of greater than 2.4 million PV components set up on single-axis trackers, with 150 inverters along with the lithium-ion battery storage space center. It would certainly be spread out throughout 2 varieties-- 500MW and also 220MW specifically-- that would certainly be attached by cabling.

The system would certainly after that attach to an existing 330kV transmission line of TransGrid-- the utility powering NSW and also the Australian Capital Territory-- that transects the growth website.

As it authorized the 720MW of brand-new solar and also 200MW/400MWh of brand-new batteries, the Commission suggested that UPC's project "would certainly not piece or estrange source lands [...] as the land could be conveniently gone back to farming land complying with decommissioning, and also the fundamental farming ability of the land would certainly not be influenced".

The preparation body additionally claimed there would certainly be "no considerable aesthetic influences" on the close-by homes. Nevertheless, it included a need for UPC to make plants testing readily available for one adjoining homeowner that would certainly be affected.

The developer will certainly additionally need to alleviate any type of transportation and also web traffic effects with a Traffic Management Plan, to be prepared in examination with Roads and also Maritime Services as well as Uralla Shire Council. Furthermore, to make certain deactivating will certainly remain in line with regional assumptions, UPC should prepare a Decommissioning and also Rehabilitation Plan within 3 years of beginning procedures.

Keeping in mind the trouble of projecting scrap worth in 30 years' time, UPC specified: "When taking into consideration the worth originated from scrap products versus the price of disposal, equipment and also work, the project could be deactivated and also restored for an internet price of about AU$ 39 million."

This would certainly be "no greater than 10% of the funding worth of the plant," included UPC.

Wollar Solar Farm bags authorization

In different information, the NSW federal government likewise relocated lately to authorize the 290MW Wollar Solar Farm. The project, including a recommended 30MW/30MWh battery storage space add-on, has actually been regarded in the general public rate of interest.

The AU$ 431 million (US$ 282 million) project is being established by Wollar Solar Development Pty Ltd, a renewable resource company established in 2017. The system lies 7 kilometres southern of Wollar Village and also is readied to develop approximately 320 building tasks. The battery storage space center will certainly additionally use dispatchable power to the National Energy Market (NEM), with both projects adding to NSW's change far from nonrenewable fuel sources.

The NSW Department of Planning, Industry and also Environment considered that Wollar's effect on the setting and also the neighborhood can be suitably reduced, countered or took care of to an appropriate degree, based on specific problems.

It stated the land could be conveniently gone back to farming land complying with decommissioning as well as it likewise thought about the aesthetic effect of the project on the bordering homes and also roadway customers to be very little.

Willar's developer will, nonetheless, need to guarantee that off-site aesthetic effects of the advancement-- consisting of the capacity for any kind of glow or representation-- are reduced and also exterior lights is minimized.

Wollar Solar Development is additionally called for to prepare an Accommodation as well as Employment Strategy for the project, with factor to consider of the advancing influences connected with various other State substantial advancement (SSD) projects in the location.

This suggested solar ranch would certainly link to an additional existing TransGrid substation, standing about 900 metres eastern of the proposition location.

Last summer season, British developer RES likewise got NSW's preparation authorization for a 200MW solar plant with a 10MW/10MWh lithium-ion battery storage space center in the state.