Covid-19 impact: Acme Solar wants to abandon record-low solar price tariff

May 27, 2020 06:37 PM ET
  • The designer intends to cancel the power acquisition agreement it checked in 2018 for a 600 MW task awarded at a tariff of Rs2.44/ kWh, as it fears Covid-19-affected commissioning of the task will certainly stretch past the six-month extension from the scheduled date enshrined in the agreement.
Covid-19 impact: Acme Solar wants to abandon record-low solar price tariff
Image: geralt/18298 images/Pixabay

Clean energy developer Acme Solar, which safeguarded a 600 MW project in Rajasthan at the lowest ever before Indian toll for solar electrical power, intends to desert the agreement. The job was nabbed in 2018 when Acme used to be paid Rs2.44/ kWh created after a reverse public auction by tendering company the Solar Energy Company of India (Seci).

Acme, however, has now approached regulator the Central Electrical energy Regulatory Commission (Cerc) seeking instructions to avoid Seci and also the Power Grid Firm of India Ltd from encashing bank guarantees and also letters of funding which it submitted to secure the contract.

In its request, the developer submitted its decision to end the power purchase contract (PPA) executed with the Seci, citing a failure to commission the project within the agreed timeline because of provide chain disturbance triggered by the Covid-19 episode as well as to hold-ups in securing land for a necessary substation in addition to the appointing of associated transmission network facilities.

Force majeure

" The petitioners [Acme Solar] have actually terminated the PPAs dated 7.12.2018, performed with Seci, therefore ... force majeure events, particularly, status orders by Rajasthan High Court [related to] land on which [the] Fatehgarh substation was to be built; episode of Covid-19 as well as its adverse impact on making facilities of vendors since December 2019, including [lockdowns] in China and India; as well as hold-up in [the] appointing of associated transmission network components by various other transmission provider," wrote the programmer in its petition.

Acme stated the jobs had actually currently been delayed 15 months on account of the non-Covid aspects mentioned, and also further hold-up would certainly be expected as a result of Covid-19-induced uncertainty.

" The PPAs got in with Seci attend to an optimum expansion of six months from arranged commissioning day, i.e., [a] overall 30 months from the reliable date of the PPAs for commissioning the entire ability of the projects, due to any reason whatsoever," proceeded the Acme petition. "Consequently, the whole capability of the projects is needed to be commissioned by 8.5.2021, thinking about an expansion of six months from the arranged commissioning date of 8.11.2020. The PPAs do not permit any expansion yet factor for any factor. As a result of postpone therefore force majeure occasions, the petitioner can not perform the jobs within the time. As necessary, the efficiency of obligations under the PPAs has come to be impossible, and hence ended up being space. Consequently, the parties are absolved from their obligations."

Seci reaction

Seci, nonetheless, has declined unilateral discontinuation of the agreement by Acme on alleged force majeure premises. The federal government's solar power body has actually contested the force majeure insurance claim as well as stated even if such an occasion was identified, its impact can not be expected to proceed for more than three months.

Seci additionally informed the regulatory authority it is considering giving a task due date extension to Acme as well as has no intent of encashing or appropriating the developer's bank warranty if the issues can be settled by common discussion.

The ultra-cheap settlements concurred by Acme for the power created by the Rajasthan task, and also considering that equated to in Gujarat, motivated experts to guess about whether such solar farms could be financially sensible.


SOLAR DIRECTORY
Solar Installers, Manufacturers