Grenergy Signs 900-GWh-a-Year Solar PPA in Peru for 15 Years

Grenergy Signs 900-GWh-a-Year Solar PPA in Peru for 15 Years

Key points

  • Grenergy signed a 15-year PPA in Peru for nearly 900 GWh of solar power a year, supplied from 2029.
  • The power comes from Macarena (209 MW) and Locumba (241 MW), which together would add about 36% to Peru's 1,241 MW of solar.
  • The buyer, price and investment were not disclosed.

Grenergy signed a 15-year power purchase agreement in Peru for nearly 900 GWh of solar power a year from its Macarena and Locumba projects, with supply due to start in 2029.

The Spanish developer announced the deal on Nov. 24, 2026, in a press release and calls it the largest renewable PPA signed to date in Peru. Grenergy did not name the buyer, an investment-grade utility. Macarena (209 MW) is in the Ica region and Locumba (241 MW) in Tacna, both in southern Peru. Neither the release nor a filing with Spain's securities regulator discloses the contract price, the investment, the construction schedule or whether the capacity is AC or DC. Only the release makes the largest-PPA claim.

Peru had 1,241 MW of solar capacity installed at 22 plants, the Ministry of Energy and Mines (MINEM) said on Nov. 19. Solar plants generated 1,442 GWh in the first half of 2026, up 87% from 771 GWh a year earlier, according to MINEM.

The contract in numbers

  • 450 MW of solar across the two projects, with expected combined output of more than 1.1 TWh a year.
  • About 80% of that output is contracted, or nearly 900 GWh a year.
  • About 82% is what 900 GWh would be of exactly 1.1 TWh, so the company's 80% implies output somewhat above that floor (list.solar calculation).
  • 13.5 TWh of solar power contracted over the 15 years at 900 GWh a year (list.solar calculation).
  • About 28% is the capacity factor that 1.1 TWh from 450 MW implies, or about 6.7 kWh per kW a day (list.solar calculation).
  • About 36% is what 450 MW would add to Peru's 1,241 MW of installed solar (list.solar calculation).

Grenergy has worked in Peru since 2015. It built the Duna Huambos wind farm in 2021 and the 100-MW Matarani solar plant in 2022, then sold both. In June it signed a 1-TWh-a-year night-time PPA in Chile, also for 15 years. Grenergy ties demand growth in the Andean region partly to new investment in mining, as in northern Chile, where it developed Oasis de Atacama.

“Signing Peru’s largest renewable PPA marks another milestone for Grenergy and reinforces our commitment to the Andean region,” said David Ruiz de Andrés, Grenergy’s chief executive officer.

Supply under the contract is scheduled to begin in 2029. Grenergy gave no date for the start of construction or commercial operation at either project.

Source

Grenergy (press release)