ACME Solar Commissions 148.6-MWh Battery for Tata Power in Rajasthan

Key points
- ACME Solar commissioned 35.81 MW / 148.645 MWh of a 50-MW / 209-MWh battery for Tata Power at Neemri on Nov. 20.
- Tata Power will pay INR 4.43 per kWh under a 25-year deal; ACME gave no project cost.
- Commercial operation was scheduled for Nov. 22; the solar part and 14.19 MW of battery are still to come.
ACME Solar Holdings Ltd. commissioned 35.81 MW / 148.645 MWh of battery storage at its 50-MW firm and dispatchable renewable energy (FDRE) project for Tata Power in Neemri, Rajasthan, on Nov. 20, 2026.
The tranche belongs to wholly owned subsidiary ACME Sigma Urja, according to a filing with BSE and the National Stock Exchange of India. Commercial operation was scheduled for Nov. 22. Only the battery storage component is running so far. Tata Power's distribution business will buy the output at INR 4.43 per kWh for 25 years, under an agreement signed on Oct. 16, 2025. The filing gives no project cost, battery supplier or solar plant size, so cost per kWh cannot be worked out.
| Commissioned (discharge) | 35.81 MW / 148.645 MWh |
|---|---|
| Commissioned (installed) | 35.81 MW / 160.48 MWh |
| Full battery | 50 MW / 209 MWh discharge (220 MWh installed) |
| Location | Neemri village, Rawatbhata tehsil, Chittorgarh district, Rajasthan, India |
| Owner | ACME Sigma Urja Pvt., wholly owned by ACME Solar Holdings |
| Offtaker and tariff | The Tata Power Company (Tata Power-D), INR 4.43 per kWh, 25 years |
| Commissioned / commercial operation | Nov. 20, 2026 / Nov. 22, 2026 (scheduled) |
India had 5,317.85 MW / 14,543.20 MWh of battery storage in operation on Sept. 30, 2026, the Central Electricity Authority reported. The count covers 19 projects of at least 1 MWh. Another 27,730.24 MW / 78,963.92 MWh was under construction.
The Tata Power battery is separate from ACME Sigma Urja's 250-MW / 1,069-MWh FDRE battery in the same village. ACME added 16.06 MW / 69.678 MWh there on Nov. 20 as well, after an 88-MW block on Oct. 30. That project now has 175.72 MW / 733.939 MWh in service. ACME's running total covers the 250-MW project only and leaves out the Tata Power tranche.
The math behind Neemri
- 4.2 hours of storage at full output: 148.645 MWh divided by 35.81 MW (list.solar calculation).
- 71% of the Tata Power battery's 209 MWh of discharge capacity is now commissioned, leaving 14.19 MW / 60.355 MWh (list.solar calculation).
- 92.6% of the tranche's 160.48 MWh installed capacity counts as discharge capacity, against 93.0% for the 250-MW project (list.solar calculation).
- 1.0% is what 148.645 MWh adds to the 14,543.20 MWh in operation nationwide on Sept. 30 (list.solar calculation).
- 400 days passed between signing the Tata Power agreement and commissioning the first battery tranche (list.solar calculation).
The contract requires a minimum annual capacity utilisation factor of 40% and four hours of peak supply at 90% monthly availability, ACME said when it signed. Across both Neemri projects, ACME commissioned 51.87 MW / 218.323 MWh on Nov. 20.
ACME's September 2025 award release gave the project 24 months from the agreement, a deadline that falls in October 2027. ACME has not given a date for the remaining 14.19 MW of battery or for the solar plant.