ZE Energy Buys 59-MW, 8-Hour Magliano Alpi Battery Project in Italy

Key points
- ZE Energy bought the permitted 59 MW / 472 MWh Magliano Alpi battery project in Piedmont from ReFeel New Energy.
- It is ZE Energy's third standalone storage project in Italy and its first in the north.
- The price, battery supplier and construction dates were not disclosed.
ZE Energy has bought the Magliano Alpi battery storage project in Italy's Piedmont region, a fully permitted, ready-to-build 59 MW / 472 MWh standalone system. The seller is ReFeel New Energy, an Italian developer backed by Gresham House Europe, the French company said in a release dated Nov. 23, 2026.
Magliano Alpi will connect to the 132 kV grid through an existing substation of Terna, Italy's grid operator. It is ZE Energy's third large-scale standalone storage project in Italy, after Sessa Aurunca and Elena, and its first in the north. ZE Energy did not disclose the price. It also gave no battery supplier, chemistry, construction start or operation date, and said nothing on how the plant will earn revenue.
| Power / energy | 59 MW / 472 MWh |
|---|---|
| Duration | Up to 8 hours |
| Location | Magliano Alpi, Piedmont, northern Italy |
| Buyer | ZE Energy |
| Seller | ReFeel New Energy (SUSI Energy Transition Fund, managed by Gresham House Europe) |
| Grid connection | 132 kV, existing Terna substation |
| Status | Fully permitted, ready to build |
| Price | Not disclosed |
Italy buys most new grid batteries through MACSE, a Terna auction for long-term storage contracts. The first round, held on Sept. 30, 2025, procured 10 GWh in southern Italy and the islands at a weighted average of €12,959/MWh-year, according to Terna. For the 2029 delivery year, Terna's needs document sets a national need of 16 GWh, with a minimum and maximum of zero for the North area. That leaves no MACSE volume in that round for a northern battery such as Magliano Alpi.
The math behind Magliano Alpi
- 8.0 hours of discharge at full power: 472 MWh divided by 59 MW (list.solar calculation).
- 4.7% is Magliano Alpi's 472 MWh against the 10 GWh awarded in Terna's first MACSE auction (list.solar calculation).
- About 172 GWh a year at one daily cycle, under 0.4% of Italy's 2025 solar output of more than 44 TWh (list.solar calculation).
- 3.9% of ZE Energy's 1.5 GW target for 2030 comes from this 59 MW project (list.solar calculation).
- 15% of Italy's power demand, which topped 300 TWh in 2025, was met by net imports, the release says, citing Terna.
"With Magliano Alpi, we are strengthening our presence in Italy through a project that can bring flexibility to the power system, as close as possible to the needs of consumers in the north of the country," said Rocco Mauro, head of M&A and business development Italy at ZE Energy.
Terna holds the second MACSE auction on Nov. 24, 2026, per ARERA. ZE Energy, which operates in France, Italy and Germany, gave no timetable for building Magliano Alpi. More on the sector is in our list of top energy storage companies and the storage hub.