Fukang 100-MW Tower CSP Plant Hits Full Load 21 Days After Hookup

Fukang 100-MW Tower CSP Plant Hits Full Load 21 Days After Hookup

Key points

  • The 100-MW Fukang molten-salt tower plant in Xinjiang reached full load on Nov. 20, 21 days after grid connection.
  • Steam ran at 523°C and 13.5 MPa; the turbine reached full output on its fourth run, Cosin Solar said.
  • No date for commercial operation or CSP-only cost was given.

A 100-MW molten-salt tower solar thermal plant in Fukang, Xinjiang, reached full load at 5:30 p.m. on Nov. 20, three weeks after it was connected to the grid.

Cosin Solar, which supplied the technology, reported the run in a release on Nov. 22; the China Solar Thermal Alliance (CSTA) published it in English. Main steam reached 523°C at 13.5 MPa. Its turbine got to 100 MW on its fourth run. China Green Development Investment Group owns the plant, which list.solar covered at grid connection on Oct. 30. Cosin's 1.675 TWh a year covers the whole 1-GW complex, including 900 MW of PV. On its own, the CSP unit should make about 120 GWh, CSTA said. Neither source gave the cost of the CSP unit, a commercial-operation date or the tariff.

Capacity100 MW, molten-salt tower, inside a 1-GW CSP and PV complex
Storage8 hours, 1,881 MWh of heat
LocationFukang, Changji prefecture, Xinjiang, China
OwnerChina Green Development Investment Group
Technology and core equipmentCosin Solar (solar field, salt storage and heat exchange)
Solar field15,697 heliostats, about 580,000 square meters of mirrors
InvestmentAbout 6 billion yuan for the whole 1-GW complex

Fukang is the third large CSP base project in Xinjiang that Cosin has helped build and bring into service. On Nov. 22, CNNC connected another 100-MW tower, at Jinghe, also in Xinjiang. Its contractor, Shouhang Hi-Tech, lists 16,179 heliostats with about 530,000 square meters of mirrors and a total investment of 6.144 billion yuan for that 1-GW complex.

Fukang at full load, by the numbers

  • 21 days passed between grid connection on Oct. 30 and full load on Nov. 20 (list.solar calculation).
  • 5,800 square meters of mirrors per MW at Fukang, against about 5,300 at Jinghe (list.solar calculation).
  • About 37 square meters per heliostat at Fukang, against about 33 at Jinghe (list.solar calculation).
  • About 6.0 yuan per watt for the Fukang complex, CSP and PV together, against about 6.14 yuan at Jinghe (list.solar calculation).

The run lays "a solid foundation for the project's transition to stable commercial operation," according to the English release.

China Green Development has not said when trial operation will end. Cosin says the plant will store heat in the day and generate at the evening peak.

Fukang CSP plant timeline

Concrete work on the 236-meter tower took 225 working days over almost a year, and full load came 21 days after grid connection.

  1. First concrete pour for the receiver tower

    Work on the tower shell and elevator shaft started.

    Source: CSTA (contractor release)

  2. Tower shell topped out

    The work took 225 days, including a four-month winter pause; the tower stands 236 meters with a 278-MW thermal receiver.

    Source: CSTA (contractor release)

  3. First receiver tube panel lifted into place

    Installation of the receiver's core heat-exchange parts began.

    Source: CSTA

  4. Plant connects to the grid and enters trial operation

    Connection came at 9:21 a.m.; both the 100-MW CSP and 900-MW PV parts were generating.

    Source: CSTA, list.solar, Nov. 5, 2026

  5. Plant reaches 100-MW full loadThis story

    Main steam ran at 523°C and 13.5 MPa on the turbine's fourth run.

    Source: Cosin Solar release, CSTA (English)