CNNC Connects 100-MW Jinghe Tower CSP Plant, Completing 2-GW Base

CNNC Connects 100-MW Jinghe Tower CSP Plant, Completing 2-GW Base

Key points

  • CNNC's 100-MW Jinghe molten-salt tower plant in Xinjiang connected to the grid on Nov. 22.
  • It has eight hours of thermal storage and 16,179 heliostats, according to its contractor.
  • The plant completes a 2-GW base that pairs 200 MW of CSP with 1.8 GW of PV.

China National Nuclear Corp. (CNNC) connected a 100-megawatt molten-salt tower solar thermal plant in Jinghe county, Xinjiang, to the grid on Nov. 22. It has started generating power.

The China Solar Thermal Alliance (CSTA) reported the connection in a news release on Nov. 23. Jinghe completes CNNC's 2-GW Bole-Jinghe base, which pairs 200 MW of concentrated solar power (CSP) with 1.8 GW of PV. Its PV reached full connection in 2025, and the Bole tower followed in July.

Shouhang Hi-Tech, which built the solar thermal section with PowerChina Sichuan Engineering, said the plant connected at 3:15 p.m. on its first attempt. CSTA and Shouhang did not disclose the cost of the CSP section alone or its expected yearly output.

Capacity100 MW, molten-salt tower
Storage8 hours, molten salt
LocationJinghe county, Bortala prefecture, Xinjiang, China
OwnerCNNC (project company Jinghe Xinhua New Energy)
ContractorShouhang Hi-Tech and PowerChina Sichuan Engineering consortium
Solar field16,179 heliostats, about 530,000 square meters; 228-meter tower
Investment6.144 billion yuan ($915 million) for the 1-GW Jinghe complex, including 900 MW of PV

Before Jinghe, CSTA counted China's CSP fleet at 2,438 MW after a 100-MW tower in Fukang, also in Xinjiang, connected on Oct. 30. That total put China ahead of Spain, the alliance said. list.solar covered the Fukang plant on Nov. 5.

Jinghe tower by the numbers

  • 800 MWh of electricity is what 100 MW running for eight hours would deliver, a nameplate-times-hours figure (list.solar calculation).
  • 10% of the base's 2,000 MW is solar thermal: 200 MW of towers next to 1,800 MW of PV (list.solar calculation).
  • About 6.14 yuan ($0.92) per watt is the blended cost of the 1-GW Jinghe complex; CSTA's 12.27 billion yuan for the full base gives 6.135 yuan (list.solar calculation).
  • About 23.7% is the capacity factor implied by the 2.08 TWh a year the project company expects from the Jinghe complex (list.solar calculation).
  • 4.1% is what Jinghe's 100 MW adds to CSTA's 2,438-MW fleet count of October (list.solar calculation).

CNNC says the eight-hour storage lets the plant run day and night and evens out the swings of PV output, according to the CSTA release. The design applies to other desert sites, the release says.

With Jinghe online, the base has entered full-capacity operation, CSTA said. Its June report put the expected output of both bases at 4.183 TWh a year.

Jinghe CSP plant timeline

Grid connection came almost three years after the solar thermal contract was awarded and about two years after the tower's concrete was finished.

  1. Xinjiang lists the Jinghe base among market-based grid projects

    The 1-GW project pairs a 100-MW tower with eight hours of storage and 900 MW of PV.

    Source: Jinghe county government

  2. Shouhang Hi-Tech and PowerChina Sichuan Engineering win the CSP contract

    The consortium won the procurement and construction contract for the 100-MW solar thermal section.

    Source: Shouhang Hi-Tech

  3. Last concrete poured on the receiver tower

    The tower is 228 meters tall, including a 44-meter receiver section.

    Source: Jinghe county government

  4. First heliostat comes off the on-site assembly line

    Each heliostat has 32.76 square meters of mirror; 16,179 were planned.

    Source: Shouhang Hi-Tech

  5. First receiver panel lifted to the tower top

    The receiver has 16 panels and a rated thermal power of 250 MWt.

    Source: Shouhang Hi-Tech

  6. CNNC's Bole 100-MW tower connects to the grid

    The 1.8 GW of PV in the two bases had reached full connection in 2025.

    Source: CSTA release

  7. Jinghe tower connects to the gridThis story

    Connection came at 3:15 p.m., completing the 2-GW Bole–Jinghe base.

    Source: CSTA release, Shouhang Hi-Tech