Squadron Energy Puts 8,000-MWh Battery Into NSW Planning System

Key points
- Squadron Energy's proposed 1,000-MW Cullen Bullen battery, with up to 8 hours of storage, entered the New South Wales planning system.
- At 8,000 MWh it would equal about 35% of the NEM's installed battery energy at the end of September.
- Squadron wants to start building in 2030 in two 500-MW stages, with operation from 2031.
Squadron Energy put a proposed 1,000-MW battery with up to 8 hours of storage at Cullen Bullen, New South Wales, into the state planning system. Its scoping report went online on the NSW Planning Portal, the company said on Nov. 24, 2026.
That report asks the Department of Planning for the requirements of an environmental impact statement, known as SEARs. The portal lists the project as SSD-10485, a State Significant Development at the "Prepare SEARs" stage, the first of eight that end in a determination. Squadron's site is about 25 km north of Lithgow, next to Transgrid's 500-kV Wollar to Mt Piper transmission line. The company release gives no cost, but the scoping report does. Neither document names a battery supplier, a construction contractor or an offtake contract.
| Capacity | Up to 1,000 MW / 8,000 MWh (up to 8 hours) |
|---|---|
| Location | Cullen Bullen, Lithgow City, New South Wales |
| Developer | Squadron Energy |
| Grid connection | Cut-in to Transgrid's existing 500-kV line |
| Technology | Likely LFP battery units |
| Estimated cost | A$1 billion to A$1.5 billion ($663 million to $994 million) |
| Timing | Construction desired in 2030, operation from 2031 |
Grid-scale batteries in the National Electricity Market exceeded 10 GW / 23 GWh by the end of the third quarter. That total includes projects still commissioning, according to AEMO's Quarterly Energy Dynamics. AEMO counted 5.3 GW of new battery storage at full output in the NEM since December 2025.
What the math shows
- About 35% of the NEM's 23 GWh of installed battery energy is what 8,000 MWh would equal (list.solar calculation).
- About 2.3 hours is the average duration of that fleet, against up to 8 hours at Cullen Bullen (list.solar calculation).
- About 19% of the 5.3 GW of new NEM batteries AEMO counted since December 2025 would match Cullen Bullen's 1,000 MW (list.solar calculation).
- A$125 to A$188 ($83 to $124) per kWh on the estimated cost, against BloombergNEF's 2025 stationary pack price of $70/kWh, a pack-only figure (list.solar calculation).
"We want to hear from local residents and businesses as we develop this proposal, understand what matters to them and identify opportunities for the project to benefit the wider community," said Sean Cross, project developer at Squadron.
Squadron plans to build in two 500-MW stages of about 12 to 18 months each. The report puts construction at up to 300 jobs. A qualified ecologist's assessment will decide whether a referral under the federal EPBC Act is needed. Squadron is awaiting the SEARs, which will set the scope of its environmental impact statement.