Key points

  • Aukera Energy closed Societe Generale financing for a 63-MWp solar plant and 40.5-MW battery near Ayr.
  • The solar plant holds a 20-year CfD at £65.23 per MWh in 2024 prices; the loan size was not disclosed.
  • Commercial operation is expected in early 2028, later than the 2026 date Aukera gave at consent.

Aukera Energy reached financial close on its Loch Fergus project in South Ayrshire, Scotland, a 63-MWp solar plant with a 40.5-MW battery that is due to start commercial operation in early 2028.

Societe Generale is financing construction and operation, Aukera said in a press release on Nov. 27, 2026. The utility-scale solar plant and the battery sit on one site about 4 km south-east of Ayr and share a grid connection. Aukera did not disclose the loan amount, the battery's MWh rating, the project cost or suppliers.

Loch Fergus Solar Farm is one of 157 solar projects that won contracts in the government's Allocation Round 7a, published on Feb. 10, 2026. Together they total 4,905.01 MW at a strike price of £65.23 per MWh in 2024 prices. Scotland won 331 MW of it.

Loch Fergus by the numbers

  • 20 years of Contract for Difference for the solar plant; the government's results list it at 45 MW, with a 2028/29 delivery year.
  • 15 years of Capacity Market agreement for the battery, won in the 2029/30 T-4 auction.
  • 12 years of battery optimisation by EDF, via PowerShift.
  • About 0.64 MW of battery power per MWp of solar, from 40.5 divided by 63 (list.solar calculation).
  • About 51 to 61 GWh a year from 63 MWp at UK solar load factors of 9.2% and 11.1% in DUKES 2026 (list.solar calculation).
  • About £3.3 million to £4.0 million a year is what that output is worth at the strike price, before inflation indexation (list.solar calculation, not a company figure).
  • About 13.6% of Scotland's 331 MW in the round is Loch Fergus (list.solar calculation).

Aukera's own estimate of approximately 57 GWh a year, given at consent in 2024, fits that range. EDF will also take the solar output under a long-term route-to-market agreement, while the battery trades in wholesale markets and the Balancing Mechanism. Aukera says Loch Fergus adds to a portfolio of over 1 GW of solar and battery storage projects in construction and operation.

"As demand for flexibility grows across the UK electricity market, hybrid projects such as Loch Fergus present compelling investment opportunities," said Aiden Yates, Aukera's managing director and head of structured finance.

The Scottish Government's Energy Consents Unit approved up to 45 MW of solar and up to 40 MW of storage on Oct. 22, 2024. Aukera then expected the plant on stream in 2026; it now targets early 2028.