ACME Solar Commissions 280.76-MWh Battery for SJVN in Rajasthan

Key points
- ACME Solar commissioned 70.19 MW / 280.76 MWh of batteries at two SJVN projects in Rajasthan.
- Only storage is running so far; the solar and other generation at both sites is still being built.
- Commercial operation starts Nov. 29; the filing gives no cost, tariff or battery supplier.
ACME Solar Holdings commissioned 70.19 MW / 280.76 MWh of battery storage at two projects in Rajasthan, India, that sell power to state-run SJVN Ltd. Commercial operation starts Nov. 29, 2026.
Subsidiary ACME Greentech Seventh brought the batteries online on Nov. 27, according to a filing with BSE that day. Both are firm and dispatchable renewable energy (FDRE) projects, which pair generation with storage to supply power on demand. So far only the storage runs; the renewable generation at both sites is still under development. The filing does not give the project cost, the tariff, the battery supplier, the cell chemistry or a date for the rest of the capacity.
| Discharge capacity | 70.19 MW / 280.76 MWh |
|---|---|
| Installed capacity | 70.19 MW / 320.96 MWh |
| Kelan, Bikaner district | 17.23 MW / 68.92 MWh of a 300-MW / 1,200-MWh project; Bikaner-III ISTS pooling station |
| Sanawara, Jaisalmer district | 52.96 MW / 211.84 MWh of a 150-MW / 600.166-MWh project; Fatehgarh-1 substation |
| Owner | ACME Greentech Seventh, wholly owned by ACME Solar Holdings |
| Buyer | SJVN Ltd. (power purchase agreement) |
| Commercial operation | Nov. 29, 2026 |
India had 2,927.85 MW / 8,660.20 MWh of batteries larger than 1 MWh installed on June 30, the Ministry of Power said in a July reply to parliament.
What the two batteries add up to, in figures
- 4 hours of discharge at full power at both sites, from 280.76 MWh divided by 70.19 MW (list.solar calculation).
- 87.5% of the 320.96 MWh installed counts as discharge capacity (list.solar calculation).
- 5.7% of the 1,200-MWh Kelan project and 35.3% of the 600.166-MWh Sanawara project are now running (list.solar calculation).
- 3.2% on top of the 8,660.20 MWh India had installed on June 30 (list.solar calculation).
- About $22.5 million for the installed packs alone at BloombergNEF's 2025 stationary price of $70 per kWh (list.solar calculation, not a company figure).
A full system with inverters and grid connection costs more than its packs. ACME disclosed two other battery commissionings on Nov. 25 and Nov. 26. One added 17.91 MW / 74.323 MWh at its Neemri FDRE project in Chittorgarh district, which list.solar covered at an earlier stage. The other brought 63.78 MW / 255.12 MWh at an NHPC project in Jaisalmer. With the SJVN sites, that is about 610 MWh of discharge capacity in three filings (list.solar calculation).
Another subsidiary, ACME Renewtech, commissioned 50.01 MW of solar on Nov. 26 at a hybrid project, also at Kelan village, with commercial operation from Nov. 28. That brings it to 250.05 MW of 300 MW, under a power purchase agreement with NTPC Ltd.
The filing sets no date for the remaining 379.81 MW / 1,519.406 MWh of discharge capacity at the two SJVN projects (list.solar calculation).