EnBW begins dealing with 187 MW unsubsidized PV plant in Germany

Mar 17, 2020 01:42 PM ET
  • The utility will certainly develop the project this year on 164 hectares of land simply beyond Berlin. It will certainly be the biggest solar park to be created beyond Germany's reward system for solar as well as renewables.
EnBW begins dealing with 187 MW unsubsidized PV plant in Germany
Image: Andreas160578, pixabay

EnBW began building today on the biggest solar park to be integrated in Germany without public aids. The German utility did not hold a groundbreaking event for the project, however the main beginning signal has actually been offered.

The 187 MW solar plant will certainly be improved 164 hectares of land in Weesow-Willmersdorf in Brandenburg, regarding 25 kilometers from Berlin. The plant's subsections will certainly be brought on the internet gradually, yet the project will certainly be completely functional this year, according to EnBW.

The subsidy-free project will certainly be constructed under an internal power acquisition agreement, however EnBW has yet to disclose the information of the setup. The firm explained the project as a landmark for PV in Germany.

"The harmony impacts as a result of the dimension of the plant as well as the more than 80% reduced expenses for photovoltaics in the past 10 years have actually added to this," stated Dirk Güsewell, head of generation profile advancement at EnBW. The firm began preparing the website in 2015.

The utility has actually granted construction-related orders to greater than 40 business, a lot of which originate from the area-- beginning with website administration, website traffic safety and security, landscape design solutions, as well as garbage disposal. The building stage will certainly offer approximately 150 work. Also after appointing, a number of workers will certainly remain on website to look after repair and maintenance.

The project will certainly include around 465,000 solar components. They will certainly be oriented to the south as well as will certainly be set up on underpinnings approximately an elevation of concerning 3 meters as well as an angle of 20 levels, EnBW claimed.

The power will certainly be fed right into 3 110-kilovolt lines taken care of by Edis Netz GmbH. 2 brand-new substations will certainly be constructed west as well as southwest of the park in the instant location of the high-voltage lines.

Furthermore, EnBW is presently laying a 7-kilometer cord path to the substation that will certainly be constructed in Blumberg area to the southwest. The 3rd link will certainly be made eventually afterwards. EnBW thinks an operating duration of 40 years for the PV plant.


SOLAR DIRECTORY
Solar Installers, Manufacturers