MN Holdings-Led Group Secures RM1.12 Billion Solar EPCC in Malaysia

Key points
- A consortium led by MN Holdings' unit entered a RM1.12 billion EPCC contract for 400 MWac of solar in Kemaman, Malaysia.
- The price works out to RM2.81 per watt-AC for plants awarded under the 1,975-MWac LSS PETRA 5+ round.
- Work starts on a notice to proceed from the clients and must finish no later than June 30, 2028.
A consortium led by a unit of MN Holdings Bhd entered into a RM1.1232 billion contract on Nov. 20 to build two solar plants totalling at least 400 MWac in Kemaman, Terengganu, Malaysia. The fixed lump-sum price covers engineering, procurement, construction and commissioning (EPCC), MN Holdings said in a filing with Bursa Malaysia.
MN Utilities Engineering Sdn. Bhd., wholly owned by MN Holdings, is the project leader with a 66% share. China Railway 11th Bureau Group Electric Engineering Co. Ltd. and DB Energy Sdn. Bhd. hold 17% each unless the three agree a different split. Their clients are RE Kemaman Sdn. Bhd. and RE Kemaman II Sdn. Bhd., both incorporated in September 2025. One plant has a contracted export capacity of not less than 250 MWac and the other 150 MWac. The filing does not name the clients' owners, the DC capacity, the equipment suppliers or the tariff.
Both plants come from Malaysia's LSS PETRA 5+ tender for utility-scale solar. That round approved 13 bidders with 1,975 MWac out of 37 bids for 4,073 MW, the energy transition ministry PETRA said on Sept. 2, 2025. It put expected investment at RM6 billion. The Chereh floating plant won in the same round.
The contract in numbers
- RM1,123,200,000 is the fixed lump-sum price for the whole consortium.
- 400 MWac combined: the 250-MWac plant is 62.5% of it and the 150-MWac plant 37.5% (list.solar calculation).
- RM2.81 per watt-AC at the minimum contracted capacity. That is EPCC only, not total project cost (list.solar calculation).
- RM3.04 per watt-AC is what PETRA's RM6 billion investment estimate implies across the round's 1,975 MWac (list.solar calculation).
- 66% is MN Utilities Engineering's share of the consortium's rights and obligations; each partner has 17%.
- About 20% of the capacity approved in LSS PETRA 5+ (list.solar calculation).
MN Holdings builds underground utilities and substations. Its press release calls the Kemaman job its largest contract to date and its first EPCC project in large-scale solar. It gave no profit estimate for this solar contract.
"With MNUE leading the consortium, we are focused on delivering the project successfully while establishing a stronger track record in the solar EPCC segment," the management of MN Holdings said in the release.
Work starts when the clients issue a notice to proceed or a limited notice to proceed. It must be completed no later than June 30, 2028.