- bp and Iberdrola started a 25-MW green hydrogen plant at bp's Castellón refinery, aiming for about 2,800 tonnes a year.
- Iberdrola's Spanish wind and solar farms supply 170 GWh a year under a PPA, down from 200 GWh in 2024 releases.
- The partners are studying more electrolysis at the site after Spain moved up to €211 million of IPCEI funding there.
bp and Iberdrola have started up a 25-MW green hydrogen plant at bp's Castellón refinery in eastern Spain and expect it to make about 2,800 metric tons of hydrogen a year.
bp announced the start on Nov. 27, 2026, in a press release. Castellón Green Hydrogen S.L., a 50/50 joint venture, owns the plant, and bp runs it. Its solar link is the power contract: Iberdrola supplies 170 GWh a year from its Spanish wind and solar farms under a PPA. Its output replaces part of the refinery's grey hydrogen, made from natural gas. Neither company named the farms, the solar share of the 170 GWh, the PPA price or a production cost per kilogram.
| Electrolysis | 25 MW; five 5-MW PEM modules from Plug Power (2024 release) |
|---|---|
| Expected output | About 2,800 tonnes of hydrogen a year |
| Power supply | 170 GWh a year, Iberdrola wind and solar farms in Spain, under a PPA |
| Owner / operator | Castellón Green Hydrogen S.L. (bp 50%, Iberdrola 50%) / bp |
| Investment | More than €70 million ($76.8 million), according to Iberdrola |
| Public grant | €15 million, IDAE programs funded by NextGenerationEU |
| CO2 avoided | About 23,000 tonnes a year (company estimate) |
Earlier releases promised a bigger power contract. At the final investment decision in September 2024, Iberdrola put the PPA at 200 GWh a year. One of its executives repeated that figure in March 2026. bp's release does not explain the cut. Spain's updated energy and climate plan targets 12 GW of electrolysers by 2030, the ecology ministry says. Castellón covers about 0.2% of that goal (list.solar calculation).
The electrolyser math
- About 61 kWh of contracted power per kilogram of hydrogen, from 170 GWh and 2,800 tonnes; the 2024 contract of 200 GWh implied about 71 kWh (list.solar calculation).
- About 78% of the year's hours is how long 170 GWh would run all 25 MW at full load (list.solar calculation).
- About €2.8 million ($3.1 million) per MW of electrolysis, based on Iberdrola's figure of more than €70 million (list.solar calculation).
- About 21% of that cost, at most, came from the €15 million grant, or €0.6 million per MW (list.solar calculation).
- About 8.2 kg of CO2 avoided per kilogram of green hydrogen, implied by the partners' 23,000-tonne and 2,800-tonne estimates (list.solar calculation).
Talks date to 2021, when bp, Iberdrola and Enagás studied a 20-MW electrolyser fed partly by a 40-MW solar plant. “The start-up of the green hydrogen plant with our partner Iberdrola further improves the competitiveness of our Castellón refinery, as we continue to deliver for our customers and shareholders,” said Brenda Stout, bp's senior vice president for refining, terminals and pipelines.
bp and Iberdrola are studying more green hydrogen output at Castellón. In June, Spain's energy agency IDAE approved moving up to €211 million of IPCEI Hy2USE funding to the site. bp's release gives no date for a second phase.
Castellón green hydrogen timeline
Operation started in November 2026, against a possible 2023 start in the 2021 study, and the contracted power fell from 200 GWh to 170 GWh a year.
bp, Iberdrola and Enagás agree to study a Castellón electrolyser
The plan was 20 MW, fed partly by a 40-MW solar plant, at about €90 million, with operation possible in 2023.
Source: Enagás release, list.solar, April 30, 2021
bp and Iberdrola sign the final investment decision
The 50/50 venture Castellón Green Hydrogen S.L. takes the 25-MW project forward.
Source: Iberdrola España release
Partners present the 25-MW plant and its 200-GWh PPA
Five 5-MW PEM modules from Plug Power, a €15 million grant and operation expected in the second half of 2026.
Construction starts on a 20,000-square-meter plot
Iberdrola puts the investment at more than €70 million.
Source: Iberdrola release
Assembly reaches 90%, with all equipment on site
Commissioning tests are scheduled to begin in May 2026.
Source: Iberdrola España release
Construction ends and commissioning begins
IDAE approves moving up to €211 million of IPCEI Hy2USE funding to Castellón for a possible expansion.
Source: Iberdrola release
bp and Iberdrola start operating the plantThis story
Expected output is about 2,800 tonnes a year on 170 GWh of wind and solar power.
Source: bp release