Spain's Renewables Lose €140 Million to Grid Curtailment, WoodMac Says
- Grid curtailment has cost Spain's renewable generators €140 million in 2026 to date, according to Wood Mackenzie.
- Constraints have stayed high since the April 2025 blackout, with over 25% of output lost at some nodes.
- Without voltage-control upgrades, curtailment could reach 6.5 TWh by 2028, five times the 2023 level.
Grid curtailment has cost Spain's renewable generators €140 million ($154 million) in lost revenue in 2026 to date, Wood Mackenzie said in an analysis published Nov. 16. Constraints have stayed elevated since the April 2025 blackout. The consultancy expects them to worsen as the next 10 GW of solar connects through 2028.
The report models grid congestion node by node and draws on REE data to October. Redispatch volumes have not returned to pre-blackout levels. Uncompensated constrained-off output stands at 4% of available renewable supply year to date, mostly solar and wind switched off and replaced by gas. At some nodes in Extremadura and Murcia, the share exceeds 25%.
About half of the 2026 curtailment stems from synchronous system needs such as inertia and voltage control, not line limits. Around 7 GW of solar and 26 GW of wind built before Royal Decree 647/2020 need inverter retrofits to provide dynamic voltage control. More than 35 GW could do it at no additional cost.
Spain added 8.8 GW of solar PV in 2025, taking grid-connected capacity above 41,500 MW by Dec. 31, according to Red Eléctrica.
The outlook in numbers
- 6.5 TWh of curtailment by 2028 if none of the 35 GW is brought to compliance, against 1.3 TWh in 2023.
- 5 times the 2023 level in that downside case (list.solar calculation).
- 18% rise in curtailment over the next two years in the same scenario.
- 24%: the 10 GW still to connect, measured against Red Eléctrica's 41.5 GW end-2025 PV fleet (list.solar calculation).
- 10 GW of batteries operating by 2030 in the base forecast and 20 GW in the high case, up from 0.2 GW in 2025.
In the base case, curtailment stabilises in 2027 and 2028, but only if voltage control keeps pace with new solar. Stress is building around Madrid, Toledo and Cáceres, and developers are moving to León, Valladolid, Huesca and Zaragoza. Grid reinforcement takes seven years on average.
"Whether curtailment stabilises in 2027 or continues rising depends almost entirely on how fast that capacity is brought to compliance," said Agustin Huerga, a research analyst for European power and renewables at Wood Mackenzie.
More than 40 GW of battery storage is under development, 25 GW of it with grid access. With synchronous condensers fully operational by 2029, curtailment is projected to fall 30% a year over the outlook, Wood Mackenzie said.
Also read
- Sonnedix Japan Starts 125-MWh Battery at Oita Solar Plant
- esVolta Closes $181 Million for 290-MW Texas Battery Projects
- US Energy Storage Passes 200 GWh as Q3 Installs Hit 14.3 GWh
- Samsung SDI Wins 16-GWh LFP Battery Order From Jupiter Power
- Ember Finds Wind Cuts Cost of Near-Firm Solar and Batteries by 18%