Tesla Megapacks chose for Edify's 300MWh Australia battery portfolio

Mar 23, 2022 03:01 PM ET
  • Tesla has been gotten to offer 150MW/300MWh of its Megapack battery energy storage system (BESS) remedy for projects in growth by Edify Energy in Australia.
Tesla Megapacks chose for Edify's 300MWh Australia battery portfolio
Image: Edify Energy

Edify Energy claimed the engineering, procurement and also building (EPC) offer authorized with Tesla Motors Australia covers three standalone lithium-ion BESS setups which will certainly be linked to an electrical substation at Darlington Point, in the Murrumbidgee Shire, New South Wales (NSW).

The 3 colocated projects in the portfolio are the 60MW/120MWh Riverina Energy Storage System 1, 65MW/130MWh Riverina Energy Storage System 2 and also the 25MW/50MWh Darlington Point Energy Storage System.

Last May, oil and gas significant Shell's consumer energies subsidiary Shell Energy signed a long-lasting services arrangement for operational legal rights to Riverina Energy Storage System 1. As reported by Energy-Storage. information at the time, it will be utilized to service Shell's long-term retail contract with the NSW government.

The relationship in between Edify and also Tesla in Australia returns to their collaborate on a battery storage retrofit at Gannawarra solar fam in Victoria, finished in 2018 and also amongst the nation's first large battery projects.

The 25MW/50MWh system at Gannawarra was based on Megapack's precursor, the Tesla Powerpack-- which is still readily available as an industrial as well as industrial (C&I) or little utility application product, but has been replaced for bigger projects with the Megapack given that its launch in 2019. Each Megapack has a maximum capacity of 3MWh.

Tesla has actually supplied some of Australia's most significant BESS projects until now including the Hornsdale Power Reserve (150MW/193.5 MWh) as well as the just-completed Victorian Big Battery (300MW/450MWh), both of which were by programmer Neoen. Megapacks will additionally be used at Genex Power's 100MWh Bouldercombe project in Queensland which has gotten to economic close in the past few weeks.

The 300MWh of battery storage at Darlington Point will play into the National Electricity Market (NEM), which covers the majority of Australia's east shore regions. The NEM already supplies revenue chances for batteries on a merchant basis for ancillary services and arbitrage, and is developing rapidly to accommodate greener and more effective grid properties like batteries as well as inverter-based renewables.

" The advantages of massive batteries in our expanding world of renewables are well documented and supported," Edify chief executive officer John Cole said.

" Energy storage is rapidly coming to be a valued capacity remedy for the National Electricity Market, provided its rapid and accurate action as well as technical capability. The speed of innovation in this growing technology class is exciting and also with it a breaking of the obstacles to acceptance from market as well as network individuals."

Smart inverters at the Darlington Point Substation projects will certainly suggest the battery systems will certainly likewise have the ability to sustain the local grid with security services traditionally played by the turning mass of thermal generation plants, offering synchronous inertia.

"Without a doubt, as the understanding of sophisticated inverters grows, we will certainly see even more smart modern technologies replacing revolving machines as well as speeding up Australia's shift to a clean energy future," Cole claimed.

A current Guest Blog for this site from Blair Reynolds, a product supervisor for inverter manufacturer SMA, explained the expanding role inverter-based innovations can play in resembling synchronous revolving machines to aid secure the grid in a low-carbon future.


SOLAR DIRECTORY
Solar Installers, Manufacturers