Satellite data exposes degree of solar project delays in Texas

Jul 12, 2022 04:24 PM ET
  • One-third of utility-scale solar projects slated to complete in Texas this year are either on hold or yet to begin, brand-new analysis has actually declared.
Satellite data exposes degree of solar project delays in Texas
Image: Lightsource bp

Climate tech analyst Kayrros has actually analyzed data and also images from the European Space Agency's Sentinel-2 satellite as well as compared this with project data from the Power Reliability Council of Texas (ERCOT) to establish the development made by solar arrays anticipated to attach to the Texas grid in H1 2022.

While ERCOT lists 9.8 GW of solar PV spread throughout 46 private projects as being set up to finish this year. From this swimming pool of projects, around 19 were set up to complete in the initial six months of the year.

Kayrros forecasts that just nine of those projects-- around 1.4 GW-- have finished up until now as well as of the 37 remaining projects slated for completion this year, 9 projects-- equal to 3GW of capacity-- are delayed by at the very least 6 months.

In overall, Kayrros recommends that an overall of 33% of capacity slated for link by ERCOT this year-- around 3.2 GW-- has either yet to start construction or quit after construction had begun, leading Kayrros to identify the capacity to be at risk.

" There are huge ramifications for solar ranch conclusion where asset supervisors, traders, and various other market individuals lack key information," Mark Taylor, VP of power transition at Kayrros, claimed.

" Difficulties at every action of the value chain develop the possibility of delay or cancellation for projects throughout the nation, with huge ramifications for electrical energy and gas rates and of course for the earnings as well as evaluation of market gamers,"