Samsung SDI Wins 16-GWh LFP Battery Order From Jupiter Power

Nov 17, 2026 02:14 PM ET
  • Samsung SDI signed a 16-GWh LFP battery supply deal with Jupiter Power, with deliveries over three years from 2029.
  • The cells will be made in Indiana; total orders from Jupiter Power now reach about 27 GWh.
  • The contract is worth several trillion won, the company said, as U.S. developers seek domestic supply.
Samsung SDI Wins 16-GWh LFP Battery Order From Jupiter Power

Samsung SDI's U.S. unit has signed a deal to supply 16 GWh of lithium iron phosphate (LFP) batteries to Jupiter Power, a developer and operator of utility-scale battery storage in the U.S. Deliveries run over three years starting in 2029, and the cells will be made in Indiana, the Korean battery maker said in a statement on Nov. 16.

Samsung SDI put the value of the contract at several trillion Korean won and gave no exact figure. With an earlier agreement, its orders from Jupiter Power now total approximately 27 GWh.

The order lands shortly after Samsung SDI started mass production of LFP cells at its Indiana plant. Until now its battery storage range was built on NCA chemistry. The company says it is the only non-Chinese maker of prismatic cells for storage in North America, and that it sources key materials outside China. Korean suppliers POSCO Future M and L&F have signed material supply deals for the LFP line.

Jupiter Power is backed by Global Infrastructure Partners, part of BlackRock. "Securing reliable, domestically manufactured equipment is central to how Jupiter Power plans and de-risks our build program," Chief Executive Officer Andy Bowman said.

Domestic battery manufacturing is expanding. U.S. cell manufacturing capacity reached 92.4 GWh after a new cell factory opened in Indiana in October, a 50% jump, according to SEIA and Benchmark Mineral Intelligence.

The order in numbers

  • 16 GWh of LFP batteries in the new contract, delivered over three years from 2029.
  • About 5.3 GWh a year on average over the delivery period (list.solar calculation: 16 ÷ 3).
  • About 27 GWh in total orders from Jupiter Power, including the earlier deal.
  • About 59% of that total comes from the new order; the earlier deal works out to roughly 11 GWh (list.solar calculation).
  • 19,700 MWh of Jupiter Power projects operating, under construction or committed, plus 110,000 MWh in development.
  • 48.3 GWh of energy storage installed in the U.S. in the first nine months of 2026, up 20% year on year (SEIA/Benchmark).

"This agreement reflects the competitiveness and supply capabilities of our locally produced prismatic LFP batteries in the U.S.," said Fabrice Hudry, president of ESS at Samsung SDI America. Neither company said which Jupiter projects will use the cells. Shipments are due to begin in 2029.