Flower, dces File Permits for 500-MW, 2-GWh Battery Near Berlin

Nov 16, 2026 02:22 PM ET
  • Flower and dces have filed building permit applications for Ragow, a 500-MW, 2,000-MWh battery storage project in Brandenburg, south of Berlin.
  • The four-hour system is larger than all the German battery capacity Flower bought or advanced in 2026.
  • Flower expects ready-to-build status in 2027 and targets commercial operation in 2029.
Flower, dces File Permits for 500-MW, 2-GWh Battery Near Berlin

Stockholm-based energy tech company Flower and German developer dces have submitted building permit applications for Ragow, a 500-MW, 2,000-MWh battery storage project in Brandenburg, south of Berlin. Flower said in a statement on Nov. 16 that it expects the project to reach ready-to-build status in 2027 and targets commercial operation in 2029.

The permits are not yet granted, and the release names no battery supplier, cost or grid connection date. Flower bought the project in 2025. Under the new agreement, dces will lead development with Flower's support, while Flower takes charge of financing, EPC, operation and commercialization. The company says Ragow ranks among the largest battery storage projects in Europe.

Large batteries in Germany compete for scarce grid capacity. Grid operators received 18,158 grid connection applications for battery storage in 2025, covering about 573.5 GW, and issued offers for 54.2 GW and 142.4 GWh, according to the Bundesnetzagentur. Germany's 28 pumped storage plants have about 6.2 GW and 147 GWh.

The project in numbers

  • 500 MW / 2,000 MWh of battery capacity planned at Ragow in Brandenburg.
  • 4 hours of discharge at full power (list.solar calculation: 2,000 MWh รท 500 MW).
  • 285 MW across the German batteries Flower bought, started building or brought to ready-to-build in 2026 (112 + 63 + 100 + 10 MW), less than Ragow on its own (list.solar calculation).
  • 5 times the energy capacity of Flower's 100-MW, 400-MWh Hamburg project, now under construction (list.solar calculation).
  • 3 GW of battery projects in the dces pipeline across Germany, built up over 12 years in the market.
  • 54.2 GW of battery capacity received grid connection offers in Germany in 2025, up 119% on 2024 (Bundesnetzagentur).

Flower entered Germany in 2025. In 2026 it acquired a 112-MW portfolio of seven projects from Chint Solar Europe and a 63-MW, 257-MWh project in Saxony-Anhalt. It also started construction in Hamburg and reached ready-to-build on a 10-MW, 20-MWh project in Saarland. A virtual tolling agreement with ENGIE secured financing for 126 MW of battery capacity in Germany.

Founder and CEO John Diklev said the need for large batteries that "can mitigate volatility, improve grid efficiency and accelerate renewable energy build-out is increasing rapidly."

Flower plans to roll out its own asset optimization algorithms in Germany in 2027. Ragow's next step is the permit decision, ahead of the ready-to-build target the same year.