Blue Elephant Energy Starts Building 96-MWp Agri-PV Cluster in Germany

Nov 16, 2026 02:24 PM ET
  • Blue Elephant Energy reached financial close for three tracker-mounted agri-PV parks totaling almost 96 MWp in Germany.
  • Commerzbank provides the financing; farm machinery will work 9-meter strips between module rows.
  • Goldbeck Solar is building the parks, with commissioning scheduled for the third quarter of 2027.
Blue Elephant Energy Starts Building 96-MWp Agri-PV Cluster in Germany

Blue Elephant Energy has reached financial close for three agri-PV parks with a combined capacity of almost 96 MWp in Mecklenburg-Western Pomerania, Germany, and construction is under way. Commerzbank is providing the financing and Goldbeck Solar is building the plants, the Hamburg-based company said in a statement on Nov. 16.

The cluster is made up of Pingelshagen at 43 MWp, Alt Meteln at 33 MWp and Klein Trebbow at 20 MWp, all near Schwerin. The company calls it Germany's largest agri-PV project with tracker-mounted modules. Neither side disclosed the size or terms of the project financing.

The modules sit on trackers that follow the sun during the day. A 9-meter strip stays free between the rows, so the farmer can keep working the land with standard machinery for the planned 30-year life of the plants.

Dual-use projects are a small but growing slice of German utility-scale solar. In the March 2026 ground-mounted tender, so-called special solar installations, a category that includes agri-PV, won 59 awards totaling 439 MW, a record for the category, according to the Bundesnetzagentur.

The cluster in numbers

  • 96 MWp across the three parks: 43 MWp at Pingelshagen, 33 MWp at Alt Meteln and 20 MWp at Klein Trebbow (list.solar calculation; the company rounds it to "almost 96 MWp").
  • 45% of the cluster's capacity sits at Pingelshagen, the largest of the three sites (list.solar calculation).
  • 9 meters of free strip between module rows for farm machinery.
  • 30 years of planned operating life, with farming and power generation on the same land.
  • 2.4 GW in Blue Elephant's portfolio in operation and under construction, plus a pipeline of more than 10 GW.
  • 19.1% of the 2,299 MW awarded in Germany's March 2026 ground-mounted tender went to special solar installations such as agri-PV (list.solar calculation from Bundesnetzagentur data).

Founded in 2016, Blue Elephant develops and operates solar, onshore wind and battery storage projects across Europe, and will also manage the three parks once they are online. Its chief investment officer, Tim Kallas, called the closing "a decisive step in realising our in-house developed agri-PV cluster."

"We are delighted to support Blue Elephant Energy as a financing partner for this forward-looking project with a tailored financing solution," said Jens Taubken, director of green infrastructure finance at Commerzbank.

Commissioning of all three parks is scheduled for the third quarter of 2027.