ACME Reaches FID on $3.6-Billion Green Ammonia Plant in Odisha

Nov 19, 2026 09:17 AM ET
  • ACME Group took a final investment decision on a 760,000-tonne-a-year green ammonia plant in Odisha, costing about $3.6 billion.
  • About 60% of output is already sold: 370,000 tonnes to Indian fertilizer makers via SECI and 83,000 tonnes to Japan's IHI.
  • Commissioning is expected by 2029, with a 2,200-tonne-a-day ammonia loop from Thyssenkrupp Uhde.
ACME Reaches FID on $3.6-Billion Green Ammonia Plant in Odisha

ACME Group has taken a final investment decision on a green ammonia plant in Odisha, India, that will make 760,000 tonnes a year at an investment of about $3.6 billion, the company said in a statement on Nov. 18. Commissioning is expected by 2029.

The plant will run entirely on renewable power. Electrolysers will split water into hydrogen, and a 2,200-tonne-a-day Haber-Bosch ammonia loop designed by Thyssenkrupp Uhde will turn it into ammonia. CertifHy, an RFNBO certification body, has confirmed that ACME's proposed power supply setup complies with EU rules for renewable fuels of non-biological origin, ACME said. The company did not disclose how much solar or wind capacity will feed the site.

Most of the output already has buyers. Solar Energy Corp. of India will take 370,000 tonnes a year for Indian fertilizer companies under the government's SIGHT incentive scheme. Another 83,000 tonnes will go to IHI, secured under Japan's long-term decarbonization power auction. Brookfield joined ACME's green ammonia platform in September with a commitment of up to $600 million.

The project in numbers

  • 760,000 tonnes of green ammonia a year, which ACME calls the largest green ammonia FID in India so far.
  • About $3.6 billion of investment, or roughly $4,740 per tonne of annual capacity (list.solar calculation).
  • 453,000 tonnes a year contracted with SECI and IHI, about 60% of capacity (list.solar calculation).
  • About 135,000 tonnes of hydrogen a year bound in that ammonia, based on its 17.8% hydrogen share by mass (list.solar calculation).
  • 5 million tonnes a year or more of green hydrogen capacity is India's 2030 target, against about 8,000 tonnes commissioned by February 2026, government data show.
  • Up to $600 million committed by Brookfield to ACME's green ammonia platform.

Odisha is the second green ammonia FID for ACME, after a 100,000-tonne first phase in Duqm, Oman, that it expects to commission soon. More solar-to-fuel projects are tracked on list.solar.

The decision moves the company "from ambition to execution at scale," said Manoj Kumar Upadhyay, chairman of ACME Group.

Construction comes next, with the plant due online by 2029. Last month, the group's listed solar arm signed a 300-MW peak power deal with SECI.